TOP100 2026 Report - Report - Page 12
NEW
2
NUCLEAR
Darlington New
Nuclear Project
$20.9 BILLION
Location: Bowmanville, Ont.
Owner: Ontario Power Generation (77.5%); Canada Growth Fund (15%); Building
Ontario Fund (7.5%)
Construction: Aecon Kiewit Nuclear Partners (Aecon and Kiewit Nuclear Canada);
GE Vernova Hitachi Nuclear Energy; AtkinsRéalis
Ontario SMR Supply Chain: 4 Directions; Voyageur Services Ltd.; Boyle Excavating
Ltd. WIllscot; Aquatech Dewatering Company Inc.; ATS Industrial Automation; Apex
Chain & Cable; Lintec Print Solutions; Petrudev Inc.; Peninsula Construction;
Walter Fedy; WJ Canada; Planet Stitch; Northern Transformers; Bentley Canada
Inc.; EXP; Hatch Ltd.; XS Soil Solutions Inc.; BWX Technologies Inc.; Sean
Hinchberger Inc.; Cropac; Clearway Construction; Smith & Long; Stinson Owl-Lite;
A6N; Gillam; Norseman; BOS Innovations; Cansel Survey Equipment; Chemetics;
Ecometrix Inc.; Global Industrial Canada; Piro Consulting; 4 REFUEL; CSI-Forterra;
Tetra Tech Canada Inc.; Salit Steel; Norvent; Cambium Indigenous Professional
Services (Cips) Inc.: Wag Qa Services Canada Inc.; Alternative Solutions Inc.;
Comtech Group Inc.; Stone Tucker Instruments; Algal Engineering Ltd.; Aquatec;
Williams Communication Services; Anish Branding; Mansteel Rebar; Algoma Steel;
Armstrong Mechanical Solutions; Hunt’s Transportation; Sarens; Arrow Custom
Machining Ltd.; Canada Building Materials; Dean Marine; Rabbit Pick Up and
Delivery Inc.; Manitoulin Transport; Superior Strategies Inc.; Warrior Engineering
Ltd.; A3F; Beacon Environmental; CN Rail; Earl O’Neil Electric Supply Ltd.; Human
Resources; Hydro One; Hydro One Networks Inc.; Isaac Operations Ltd.; Jensen
Hughes Consulting Canada Ltd.; Kinectrics; Nuclear Promise X Inc.; Rite Way
Freight; Worley Canada Services Ltd.; WSP Canada Inc.; Okwaho Aluma; Peninsula
Fencing; PDI; Indigenous Marketing Solutions
Other Key Players: Arcadis (risk advisor); R.V. Anderson Associates Ltd. (consulting
engineer); TULLOCH (survey support); E.S. Fox; Egis
Legal: Borden Ladner Gervais (for AtkinsRéalis/EPC Contractor)
Substantial Completion: 2030 (first SMR)
12
RENEW CANADA – TOP100 2026
OPG
The Darlington New Nuclear Project will see the construction of four small
modular reactors (SMRs), that will produce 1,200 megawatts (MW) of electricity.
The Darlington SMR will be a GE Hitachi BWRX-300 reactor. All site grading
for future units is now complete, along with the first phase of geotechnical
investigations. Excavation work on the first unit’s reactor building shaft has
reached 80 per cent completion. Fabrication of basemat modules—which will
serve as the foundation of the first unit’s reactor building—continues to progress
with completed modules being assembled in the pre-assembly building. Once the
reactor building shaft is wholly excavated, the fully assembled basemat will be
lifted by heavy crane and placed at the bottom of the shaft in early 2026.