TOP100 2024 Report - Report - Page 40
Fraser River
Tunnel Project
$4.15 BILLION
The Ministry of Transportation and Infrastructure announced on August 18, 2021,
that a new, eight-lane immersed tube tunnel (ITT) will replace the existing George
Massey Tunnel on Highway 99, providing people a toll-free crossing that aligns
with regional interests and an active transportation connection across the Fraser
River. On September 14, 2023, the Project received a Readiness Decision from the
20
2023 Rank: 19
Location: Richmond and Delta, B.C.
Owner: Province of British Columbia (The Transportation Investment Corporation is leading
the delivery of the project on behalf of the Ministry of Transportation and Infrastructure)
Owner’s Engineer: COWI (immersed tube tunnel); R.F. Binnie & Associates Ltd.
(highway and civil work)
Other Key Players: Golder-a WSP company (archeology & heritage/geotechnical
services); Sartori Environmental Inc. (independent Environmental monitor for the
corridor improvement projects; TyPlan Consulting (marine navigation advisor);
Lucent Quay Consulting Inc. (communication and engagement services—Highway
99 tunnel project/Steveston Interchange project); Northwest Hydraulic
Consultants Ltd. (hydrotechnical and river hydraulics services); RAM Engineering
Ltd. (marine construction advisor); Wood E&I (WSP) (consulting engineer); Charter
PDI; McElhanney; GeoVerra (quality control); Turner & Townsend (cost consultant)
Legal: Bennett Jones
Funding: Public
Substantial Completion: 2030
Environmental Assessment Office. This moves the project into the Process Planning
phase of the EA process. In the interim, the Province is also taking action to reduce
traffic congestion and improve transit and cycling infrastructure along the Highway
99 corridor. Work on these improvements is underway, with two of the three transit
and cycling improvement projects have already been completed.
LRT
Surrey Langley
SkyTrain Project
$4 BILLION
2023 Rank: 20
Location: Surrey/Langley, B.C.
Owner: Province of British Columbia (The Transportation Investment Corporation is
leading the delivery of the project on behalf of the Ministry of Transportation and
Infrastructure)
Engineer: Hatch (lead engineer); Westco, DIALOG; AECOM (design); COWI (owner’s)
Other Key Players: Deloitte; Golder-a WSP company (geotechnical studies);
McElhanney Consulting Services; Ausenco; Charter PDI; Hanscomb (cost
consultant); Morrison Hershfield (early works); Parsons; Colliers Project Leaders;
EY (advisory services); GeoVerra (early works)
Legal: Norton Rose Fulbright; Borden Ladner Gervais
Funding: Public
Substantial Completion: 2028
RENEW CANADA – TOP100 2024
BC MINISTRY OF TRANSPORTATION AND INFRASTRUCTURE
The Surrey Langley SkyTrain Project is a 16-kilometre extension of the Expo Line primarily along Fraser
Highway from King George Station in Surrey to 203
St. in Langley City Centre. With an elevated guideway,
eight new stations, and three new transit exchanges,
travel time between Langley City Centre and Surrey
City Centre will be 22 minutes. Advance works continue
including the relocation of utilities (including transmission, distribution, and telecommunications lines), and
the property acquisition process. The Surrey Langley
SkyTrain Project will be delivered through three separate contracts – one for the guideway, another for the
stations, and a third for the design and installation of
SkyTrain systems and trackwork. Contract awards are
expected in 2024 along with the start of early works
and major construction.
40
BC MINISTRY OF TRANSPORTATION AND INFRASTRUCTURE
19
HIGHWAY