This new LRT, located along Finch Avenue West in the city’s northwest end, will be
integrated with the city’s existing transit system. The project includes 11 kilometres
of new semi-dedicated rapid transit between Humber College and the new Finch
West subway station on the Toronto-York Spadina subway extension; 18 surface stops
and a below-grade interchange station to connect with the new Finch West subway
station; and a maintenance and storage facility for the light rail vehicles. Construction
is making progress throughout the Finch West LRT project, including road widening, continued utility relocations and upgrades, and excavating the underground
interchange station at Finch West Subway Station. In summer 2021, the first light rail
vehicle arrived at the Finch West Maintenance and Storage Facility.
24
2023 Rank: 22
Location: Toronto, Ont.
Owner: Metrolinx
Procurement Agent: Infrastructure Ontario
DBFM Team: Mosaic Transit Partners–ACS Infrastructure Canada Inc.; Aecon
Concessions; CRH Canada Group Inc.
Construction: Aecon Infrastructure and Management Inc.; Dragados Canada
Inc.; Dufferin Construction Company—a division of CRH Canada Group Inc.
Design: Arup Canada Inc.; Dillon Consulting Limited; DPM Energy Inc.; DTAH;
Perkins + Will Canada Inc.; Sener SES Canada Inc.
Maintenance: ACS Infrastructure Canada Inc.; Aecon O&M—a division of Aecon
Construction Group Inc.
Engineer: Jacobs (owner’s engineer and project manager); WSP (engineer/
sustainability consultant/project management/TTC operator’s representative);
Hatch (owner’s engineer); LEA (engineer design); EXP
Other Key Players: AECOM (technical advisor); Aon (risk/insurance advisor
to authority); EY (advisor); LeighFisher (lenders technical advisor); Parsons
(overseeing technical advisor); INTECH Risk Management (insurance
advisor); Morrison Hershfield (MEP design services); GHD (traffic mgmt.); GFL
(excavation, shoring, soil management); Comtech (program/project consulting);
Rider Levett Bucknall; Englobe; A. W. Hooker Associates Ltd. (cost consultant);
CIMA+; Deloitte (management consultant); Entuitive; HKA; INFRATA (managing
consultant); Turner & Townsend (project controls); Matrix Solutions Inc.
(environmental specialists)
Supplier: Bombardier (vehicles); Dufferin Concrete; DECAST (precast
infrastructure); SEMP Ltd. (consulting engineer)
Legal: Norton Rose Fulbright; McMillan LLP (for the lender); Borden Ladner
Gervais (for the owner); Dentons
Funding: P3
Substantial Completion: 2024
METROLINX
Finch West LRT
$3.43 BILLION
LRT
Hamilton LRT
$3.4 BILLION
In September 2021, Hamilton City
Council voted to reinitiate the project
after it was previously cancelled by the
province in 2019 due to rising costs.
The LRT, as proposed, would bring 14
kilometres of rapid transit to Ontario’s
fifth-largest city. Once complete, the new
LRT line will connect McMaster University
in the west to Eastgate in the East, with
17 stops planned on the route. Demolition
of Metrolinx-owned properties along the
Hamilton LRT route began in the Spring of
2022, along with early construction works
for utility relocations.
In the coming years, these properties
will be required for station stops, infrastructure, and widening to accommodate
the future LRT right of way. In the short
term, demolition sites will be restored,
secured with fencing, and monitored by
security contractors.
44 RENEW CANADA – TOP100 2024
2023 Rank: 23
Location: Hamilton, Ont.
Owner: Metrolinx
Procurement Agent: Infrastructure Ontario
Other Key Players: AECOM, Wood E&I (WSP) (consulting engineer/geotechnical
studies); Arcadis-IBI Group; Comtech; Hatch; Turner & Townsend (project
controls/estimating); Dillon Consulting (design engineer)
Legal: Borden Ladner Gervais (for the owner)
Funding: Public
• Federal: $1.7 billion
• Provincial: $1.7 billion
Substantial Completion: TDB