TOP100 2024 Report - Report - Page 56
NEW
38
WATER/WASTEWATER
Northwest Langley Wastewater
Treatment Plant
$2.3 BILLION
The Northwest Langley Wastewater Treatment Plant, which currently serves 30,000
people, is being expanded to serve over 280,000 people, including residences and
businesses in the Township of Langley, Maple Ridge, Pitt Meadows and North Surrey.
The plant expansion is one of several projects taking place to improve the sustainability and resilience of wastewater treatment in the region. To divert the flows to the Northwest Langley Wastewater Treatment Plant, a new pump station is being built north of
the Fraser River in Maple Ridge. Two new sewer pipes are being constructed under the
Fraser River to connect the pump station in Maple Ridge to the upgraded treatment
plant in Langley. A new storage tank, located with the pump station, will temporarily
store wastewater to significantly reduce overflows during storms.
Location: Township of Langley, B.C.
Owner: Metro Vancouver
Construction Manager: Delve Underground (Fraser River Crossing), Stantec
(Pump Station and Storage Tank), Jacobs (WWTP Ground Improvements)
Contractors: Pomerleau (Fraser River Crossing and WWTP Ground
Improvements), NAC (Pump Station and Storage Tank)
Engineers: Delve Underground (Fraser River Crossing), CDM Smith (Outfall),
Stantec (Pump Station and Storage Tank), Jacobs
(Wastewater Treatment Plant)
Other Key Players: Carollo (Program Management), Katzie Development
Limited Partnership (Archaeological Services); WSP (program management/
technical support services); Entuitive
Legal: Cassels; Norton Rose Fulbright (owner)
Funding: Public
Substantial Completion: 2023 (Pump Station and Storage Tank), 2023 (Fraser
River Crossing), 2029 (Outfall), 2030 (Wastewater Treatment Plant)
NEW
39
HIGHWAY
Reconstruction of the
Île-aux-Tourtes Bridge
$2.3 BILLION
Location: Montréal, Québec
Owner: ministère des Transports et de la Mobilité durable
Contractor: Groupe Nouveau Pont Île-aux-Tourtes (Dragados Canada
inc., Roxboro Excavation inc., Construction Demathieu et Bard (CDB); ACS
Infrastructure Canada
Engineer: Tetra Tech-Cima+-Aecom (owner’s engineer); Arup / FNX-INNOV
(Independent certifier); WSP (consulting engineer-Phase I/technical support
services)
Other Key Players: Strategia conseil (risk and financial advisor); PriceWaterhouse (management consultant); Marsh (insurance consultant); AGAT Labs
Legal: Gowling WLG
Funding: Public
Substantial Completion: 2030
The Île-aux-Tourtes bridge, which was commissioned in 1965,
is located on autoroute Félix-Leclerc (autoroute 40) and links the
island of Montréal (village of Senneville) and the Montérégie region
(city of Vaudreuil-Dorion). This key structure is part of the strategic
road network supporting trade. To ensure its sustainability, it will
be rebuilt north of the existing bridge. The new bridge will include:
three lanes in each direction; a multipurpose path; and wide shoulders designed for bus traffic only.
40
HEALTHCARE
Nouveau complexe hospitalier
CHU de Québec-Université Laval
$2.239 BILLION
The New Hospital Complex (NCH) aims to consolidate the activities of L’Hôtel-Dieu de Québec and the Enfant-Jésus Hospital on the same site. The NCH will
become a reference center for several specialties including nephrology, neurology,
oncology, traumatology, and burns.
The project places the patient and employee at its heart to innovate in healthcare
and research, and above all, to provide even better care for the population of eastern
Quebec. With a total of 174,983 square meters of new constructions and the redevelopment of almost a third of the existing buildings, the NCH will have 700 hospital beds,
including 105 critical care beds, 30 operating rooms and 60 emergency stretchers.
56
RENEW CANADA – TOP100 2024
2023 Rank: 32
Location: Quebec City, Que.
Owner: CHU de QuébecUniversité Laval
Project Manager: Société québécoise des infrastructures (SQI)
Construction Manager: (Phase 1)
Pomerleau
Construction Manager: (Phase 2)
Groupe Axor Inc.
Commissioning Officer: Ambioner;
Pageau Morel et associés inc.
Architect: AES Group-Groupe A/
Annexe U; DMG architecture; Lemay ;
Jodoin Lamarre Pratte architectes ;
NFOE Inc. ; GLCRM Architectes
Civil engineering and structure:
CIMA+; Stantec
Mechanical and Electrical Engineering: AtkinsRéalis; Bouthillette
Parizeau; Tetra Tech
Other Key Players: Englobe (geotechnical/environmental investigation, quality control); GHD (vibration monitoring); Golder-a WSP
company (geotechnical studies);
Deloitte; Arium Design (wayfinding
consultant)
Funding: Public/Private
Substantial Completion: 2029
TOP100PROJECTS.CA