SUBWAY
Réno-Systèmes and RénoInfrastructures Programs
$1.66 BILLION
The STM has implemented three programs for asset maintenance and development of the metro network. The Réno-Systèmes program’s objective is to replace and
refurbish the metro’s fixed equipment that has reached or exceeded its lifecycle. The
Réno-Infrastructures program was set up to intervene preventively on all infrastructures. The Metro Accessibility program is directly devoted to the development of the
level of service and improving the custom.er experience in terms of universal accessi-
50
bility by integrating elevators into stations that already exist and are in operation, as
well as the integration of new pieces of art in those stations.
PUBLIC SPACES
Place du Portage III Renewal
$1.6 BILLION
The Portage III complex, currently serving as Public Services and Procurement Canada’s headquarters, is the largest
of the four buildings that comprise the Place du Portage
federal campus in Gatineau, Que. Built in the 1970s, the
complex consists of: nine towers; commercial areas; four
basement levels; and a three-level underground parking
garage. The renewal of Portage III encompasses a complete
overhaul of both the inside and outside of the building,
including modernized activity-based workplaces; a new energy-efficient building envelope and heating; (HVAC) system;
a new accessible entrance and a completely revamped main
entrance; and improved landscaping.
51
2023 Rank: 42
Location: Montreal, Que.
Owner: Société de transport de Montréal (STM)
Engineer: STM, Consortium: AtkinsRéalis-Stantec; WSP-Systra JV
Other Key Players: Bairn Architecture et Design; CIMA+; Englobe (quality
management services)
Funding: Public
Substantial Completion: 2026
2023 Rank: 62
Location: Gatineau, Que.
Owner: Government of Canada
Project/Construction Manager: BGIS
Other Key Players: Perkins & Will, Provencher, EllisDon Corporation; Arup; Tiree
(project management support services)
Funding: Public
Substantial Completion: 2027
PUBLIC SPACES
Macdonald Block
Reconstruction Project
$1.536 BILLION
2023 Rank: 44
Location: Toronto, Ont.
Owner: Ontario Ministry of Public and Business Delivery Services
Project/Construction Manager: Infrastructure Ontario
DBFM Team: Fengate PCL Progress Partners (FP3)
Developers: Fengate Asset Management and PCL Investments Canada Inc.
Design-Builder: PCL Constructors Canada Inc.
Design Architect: WZMH Architects
Facilities Management: Johnson Controls Canada
Financial Advisor: National Bank Financial
Engineer: TMP (mechanical); LEA Consulting (engineer-consulting & structural)
Other Key Players: Aon (risk advisor); Hanscomb; E.S. Fox; Morrison Hershfield;
Entuitive; EY (management consultant); Comtech (project management
consultant); WSP (independent certifier); Turner & Townsend (cost control/
management); Mulvey & Banani; HKA (management consultant)
Funding: P3
Substantial Completion: 2024
The Macdonald Block Complex is the hub for administrative services for the
Government of Ontario. The complex consists of five buildings, including four office towers,
with a total of approximately $1.7 million square feet. Each building in the complex will be
taken back to its original building core, remediated, and rebuilt using modern technologies,
systems and materials while preserving the integrity of its many heritage features.
The newly reconstructed complex will meet current building, health, safety, and
accessibility standards and will accommodate more employees through more
efficient use of this government-owned office space.
TOP100PROJECTS.CA