TOP100 2024 Report - Report - Page 62
52
SUBWAY
Bloor-Yonge Station Capacity
Improvements
$1.5 BILLION
Bloor-Yonge Station will be undergoing a design retrofit and significant expansion
to meet both current and future ridership demand. The Bloor-Yonge Station project
includes the construction of a new Line 2 passenger platform and the expansion of
both Line 1 passenger platforms, enhancements to the concourse level, entrances, exits
and improved accessibility features. Advanced construction started in May 2023, and
includes the removal of the buildings at 81 Bloor Street East and 40 and 42 Hayden
Street to construct a new, accessible subway entrance as a part of the larger project.
53
HEALTHCARE
Royal Columbian Hospital
Redevelopment Project
$1.49 BILLION
The Royal Columbian Hospital redevelopment is a threephase, multi-year project that will increase the hospital’s
capacity by approximately 50 per cent, introduce advanced
medical technologies and improve the health care environment
for staff and patients. Phase 1’s Mental Health and Substance
Use Wellness Centre opened in August 2020. Phase 2, now
under construction, will create the new Jim Pattison Acute Care
Tower with more beds, a larger Emergency Department and
more operating rooms. Phase 2 is expected to be complete in
2025. Phase 3 will upgrade and expand areas in existing buildings to support the beds and services in the new acute care
tower. Phase 3 construction is expected to begin in 2024.
54
2023 Rank: 45
Location: Toronto, Ont.
Owner: Toronto Transit Commission
Owner’s Engineer: AECOM
Other Key Players: AECOM (preliminary design and early works); Golder-a WSP
company (geotechnical studies);
WSP; CIMA+
Funding: Public
Federal: $500 million
Provincial: $449 million
Municipal: $564 million
Substantial Completion: 2029
2023 Rank: 47
Location: New Westminster, B.C.
Owner: Fraser Health Authority
Design-Build Team: EllisDon Design Build Inc.
Architects: Parkin Architects Ltd.; HDR; Arcadis-IBI Group
Other Key Players: WSP (owner’s technical advisor); EY (management
consultant); Victaulic (supplier); GeoVerra (quality control); ULMA Construction
Legal: Bennett Jones
Funding: Public
Substantial Completion: 2025
HEALTHCARE
Cowichan Hospital
Redevelopment
$1.45 BILLION
The Project consists of a replacement
community-level acute care hospital,
with capacity for 204 inpatient beds,
built to modern clinical and technical
standards on a greenfield site in the Municipality of North Cowichan. The facility
will provide patient care and programs
to address future service needs for the
region while including the following: total
building area of approximately 56,448
square metres; capacity for core inpatient
and ambulatory services, including seven
operating rooms, and additional procedure
rooms and outpatient/ambulatory clinic
62 RENEW CANADA – TOP100 2024
2023 Rank: 69
Location: Municipality of North Cowichan, B.C
Owner: Island Health
Alliance Team: EllisDon, Parkin Architects, BC Infrastructure Benefits and
Infrastructure BC
Other Key Players: Entuitive, WSP; Bird Construction; Hanscomb (cost
consultant); Mulvey & Banani; Victaulic (supplier); EY (management consultant)
Legal: Borden Ladner Gervais (legal advisor-designers); Norton Rose Fulbright
(owner’s advisor)
Funding: Public
Substantial Completion: 2026
capacity, expanded diagnostic imaging, and expanded emergency department
capacity.
EllisDon Corporation and Parkin Architects Western Ltd, were awarded the
contract to design and construct the hospital after a competitive process in
which multiple proponents submitted bids and designs under an Alliance project
delivery model. Under this delivery model, the project owner (Island Health
and the Province of BC) and the private sector share risks and opportunities,
operating as a fully integrated team to complete the project.