TOP100 2023 Report - Report - Page 74
2023
Canadian Joint Incident Response
98 Unit Infrastructure Project $415 million
NEW
Location: Trenton, Ont.
Owner: Department of National Defence
Project Contract Management: Defence Construction Canada
Contrator: Pomerleau
Engineers: Stantec (under contract with Pomerleau as a Modified Design Build)
Funding: Public
Substantial Completion: 2029
This project will see the construction of approximately 30,000
square metres of modern and secure training facilities and
spaces to support the Canadian Joint Incident Response Unit
(CJIRU) at 8 Wing Trenton.
This construction will include general facilities like office areas, meeting rooms, and a wash bay; training facilities; physical
training facilities; warehouse space; and more.
The conceptual contract design for this project was awarded
to Pomerleau Inc. in August 2019.
99 Champlain Bridge Deconstruction Project $400 million
2022 Rank: 99
Location: Montreal, Que.
Owner: Jacques Cartier and Champlain Bridges Incorporated
(JCCBI)
Construction Manager: CCF (Consortium CIMA+, FNX Innov)
Contractor: Nouvel Horizon St-Laurent GP: Pomerleau, Delsan
A.I.M. Environmental Services Inc.
• Engineer: American Bridge Company, SNC-Lavalin, T.Y.Lin
International Group, Harbourside, ARUP
• Design: Universal Structures Inc.
Engineer: PTA – Parsons, TeraTech, Wood-a WSP company
(environmental); McElhanney (consulting)
Other Key Players: Aon (risk advisor); EY (mgmt. consultant)
Supplier: Canam Group
Funding: Public
Substantial Completion: 2024
100 Fairbank Silverthorn Storm Trunk Sewer System $400 million
NEW
Location: Toronto, Ont.
Owner: City of Toronto
Contract 1: EBC Bessac Joint Venture (Quebec/France)
Contracts 2 & 3: In procurement
Environmental Services: United Soils Management
(soil disposal subcontractor)
Funding: Public
Substantial Completion: 2026
The City of Toronto, with support from the Government of Canada, is making a significant investment in storm water infra-
74 ReNew Canada
structure to protect the Fairbank-Silverthorn community from
basement and surface flooding. The project will construct a
three-kilometre long and 4.5-metre diameter storm trunk sewer,
17-km length of storm collector sewers and install 325 inlet control devices to control stormwater going to catch basins. When
construction is complete, the new infrastructure will help to reduce sewer backups and basement flooding for more than 4,645
homes and provide flood protection to a 140-hectare area. The
first contract to construct the storm trunk sewer and some storm
collector sewers is underway. Several shafts have been completed and others are being constructed in anticipation of tunneling
work, set to commence in early 2023.
JCCBI
The Champlain Bridge (also known as Pont Champlain) was a
steel truss cantilever bridge with viaducts constructed of prestressed concrete beams. It crosses the Saint Lawrence River,
connecting the Island of Montreal to its South Shore suburbs.
Opened in 1962, the structure was degraded by de-icing salt. In
2015, construction began downstream on a replacement bridge
designed to handle higher volumes of traffic. The replacement
bridge opened on July 1, 2019, and the old Champlain Bridge
was closed to traffic. The deconstruction project of the bridge
will consist of three methods:
1. The deconstruction of the shoreline sections will be carried
out from jetties set up along the river using standard equipment
(excavators and cranes.)
2. Work from the river, which will be required for over 65 per
cent of the project, will be done with a system of platforms attached to high-capacity lifting towers installed on a catamaran
barge.
3. In January 2022, the main span located over the Seaway, the
enormous 117.5-m long and 2,200-tonne component, was lowered 33 metres with strand jacks installed on anchor spans on
each side, onto an assembly of two barges in the middle of the
Seaway.