TOP100 2026 Report - Report - Page 81
MTMD
95
METROLINX
Route 389
Improvement Program
$738 MILLION
Route 389 connects the town of BaieComeau and the border of Newfoundland
and Labrador over a distance of 570
kilometres. The program is divided into
five separate projects carried out in
parallel: Project A—from Fire Lake to
Fermont; Project B—from Baie-Comeau
to Manic-2; Project C—north of Manic-5,
from kilometre 240 to kilometre 254;
Project D—from Manic-2 to the north of
Manic-3; and Project E—from north of
Manic-3 to Manic-5.
96
Bowmanville
Extension Project
$730 MILLION
2025 Rank: 92
Location: Bowmanville, Ont.
Owner: Metrolinx
Advance Infrastructure Planning Contract:
Bowmanville Construction Partners (BCP)—Ledcor
CMI Ltd. and FlatironDragados
Other Key Players: Wood (WSP) (consulting
engineer/geotechnical studies/environmental
assessment [TPAP Addendum]); Stantec (technical
advisory Services); Deloitte, Golder (WSP)
(environmental assessment), WSP (geotechnical
services); AECOM; Hatch (consulting engineer);
Accenture (project manager); Egis; XS Soil
Solutions; Strata Drilling Group; E.S. Fox; Arup
(engineer-planning)
Funding: Public
Substantial Completion: TBD
REMEDIATION
Faro Mine
Remediation Project
$700 MILLION
Faro Mine is a former open-pit lead-zinc mine, one of the largest of
its kind in the world at approximately 25 square kilometres. It is located
in south-central Yukon on the traditional territory of the Kaska Nations,
near the town of Faro. Abandoned in 1998, resource extraction led to 70
million tonnes of tailings and 320 million tonnes of waste rock. Care and
maintenance work since then has helped to ensure water quality so that
environmental standards are met. Active remediation is expected to begin
in 2025 following the successful completion of the Yukon environmental
and socio-economic assessment process, and receipt of a water licence
from the Yukon Water Board. Remediation is expected to take about 15
years to complete, followed by ongoing testing, maintenance operations
and monitoring to make any needed improvements to the site.
TOP100PROJECTS.CA
2025 Rank: 91
Location: Baie-Comeau, Que. To the N.L. border
Owner: Ministère des Transports et de la Mobilité durable (MTMD)
Contractor: Dexter Québec (project A, section 3 and project C); cooperation
agreement with the Innu Takuaikan Uashat mak Mani-utenam Council (project A,
sections 1 and 2) Groupe Alfred Boivin (project B)
Other Key Players: BPR/AXOR Experts-Conseils Consortium (planning and
specifications north of Manic-5); Roche-TDA Consortium, in conjunction with
Inspec-Sol (GHD) (Environmental assessment); WSP (route design work);
AECOM (consulting engineer); Englobe/ AtkinsRéalis (quality control and
materials engineering-project A, section 3); Norda Stelo/CIMA+/Tetra Tech (work
monitoring-project A, section 3); Stantec (design/planning engineer)
Legal: Lavery
Funding: Public
Federal: $183 million (New Building Canada Fund, Provincial-Territorial
Infrastructure Component—National and Regional Projects)
Provincial: $555.1 million
Substantial Completion: 2028
RAIL
The Bowmanville Extension will extend
the Lakeshore East GO Line nearly 20 kilometres to Bowmanville and includes: new
track and signal infrastructure; seven new
bridges, including a new rail alignment
over Highway 401; bridge reconstruction and existing bridge modifications;
utility relocations; and at-grade crossing
upgrades. In 2024, GO Transit announced
that works would begin on the future
Ritson Road GO Train station.
97
PSPC
HIGHWAY
2025 Rank: 93
Location: Faro, Yukon
Owner: Government of Canada
Project/Construction Manager: Construction and Care
and Maintenance Manager: Parsons Inc.
Engineer: Remediation Design Engineer: AECOM
Canada Ltd.
Other Key Players: Ensero Solutions Canada Inc.
(environmental monitor); CH2M Hill Canada Ltd. (water
treatment plant designer), Tetra Tech Canada Inc., WSP
(geotechnical); Golder (WSP) (environmental assessment/
regulatory support services); Tiree/Colliers Project Leaders
(performance management services and contaminated site
project valuation); Victaulic (supplier); AGAT Labs (geotechnical studies/materials tester); McElhanney (site surveyor);
KPMG; Turner & Townsend (cost consultant)
Funding: Public
Substantial Completion: 2039
RENEW CANADA – TOP100 2026