TOP100 2026 Report - Report - Page 72
CFB Esquimalt A/B Jetty
Recapitalization Project
$1.1 BILLION
The aim of the A/B Jetty project is to demolish and
replace the old A and B jetties at CFB Esquimalt’s Dockyard,
which were constructed during World War II. The A/B Jetty
project supports Canada’s National Shipbuilding Procurement
Strategy, which is delivering modern ships to the Royal Canadian Navy over the next 30 years. The new fully integrated A/B
Jetty facility will be home to several of these Canadian-built
vessels, including the new Arctic/Offshore Patrol Ship and
Joint Support Ship, and in due course the future Canadian
Surface Combatant ships.
72
2025 Rank: 69
Location: Esquimalt, B.C.
Owner/Project Manager: Department of National Defence
Contractor: Pomerleau (B Jetty construction)
Project Contract Management: Defence Construction Canada
Engineer: Stantec (design authority for B Jetty); Wood E&I (WSP) (design
authority for A Jetty)
Other Key Players: Hanscomb (design engineer’s cost consultant for A Jetty);
Arcadis (design engineer for B Jetty); Golder (WSP) (geotechnical studies/
environmental engineering); Anchor QAE (environmental advisor); Hemmera
(environmental); HDR (risk advisor); WSP (commissioning agent); Ruskin/CDI,
RIC Power, Trotter & Morton, Black & McDonald (subcontractors to Pomerleau);
Englobe; EY (management consultant); McElhanney; GeoVerra (site surveyor);
Turner & Townsend (cost consultant)
Funding: Public
Substantial Completion: 2029
POMERLEAU
71
MILITARY
HEALTHCARE
Toronto Western
Hospital Patient Tower
$1.1 BILLION
2025 Rank: 70
Location: Toronto, Ont.
Owner: University Health Network
Construction Manager: EllisDon
Design: DIALOG
Other Key Players: Aon (risk advisor); H.H. Angus &
Associates Limited Consulting Engineers (engineerdesign); Hanscomb (cost consultant); Stantec
Funding: Public
Substantial Completion: 2028
UHN
Once complete in 2028, the new 15-storey tower
will add: 82 patient beds, including new critical care
beds; 20 state-of-the-art operating rooms, including
three new image-guided operating rooms for complex
neurosurgical and spinal procedures; and new single
patient rooms.
NEW
PPAW 1 Wind
Energy Centre
$1.1 BILLION
The Pohénégamook-Picard-Saint-Antonin-Wolastokuk (PPAW) Wind Energy Centre is a 350-megawatt
wind energy project located in the Bas-Saint Laurent
region in Quebec. The project was selected by Hydro-Quebec in 2023 to contribute to Quebec’s energy
transition plan. PPAW 1 is expected to distribute
$137 million to the Alliance de l’énergie de l’Est, a
consortium of 209 municipalities and territories in
Eastern Quebec, from the Montmagny Regional County
Municipality (RCM) to the Côte-de-Gaspé RCM, including the Wolastoqiyik Wahsipekuk First Nation and the
Communauté maritime des Îles-de-la-Madeleine.
72
RENEW CANADA – TOP100 2026
2025 Rank: 70
Location: Bas-Saint Laurent, Que.
Owner: Invenegy / Allica Alliance de l’énergie de l’Est
Contractor: CRT-FGL Consortium (CRT Construction
and Groupe Gilbert)
Other Key Players: Vestas (wind turbines); Marmen
Énergie (wind towers); Pesca; BBA; Groupement
forestier de Temiscouata and Waptok; Gervais Dube;
Beton Provincial; RPF Ltee; Grues Guay; Transport
Bellemare; Construction Marcel Charest et Fils
Financing: Desjardins Group; National Bank
of Canada; CIBC; Sumitomo Mitsui Banking
Corporation; KfW IPEX-Bank GmbH.
Funding: Public/Private
Substantial Completion: 2026
INVENERGY
73
WIND
TOP100PROJECTS.CA