This crossing is the largest and most ambitious binational border infrastructure
project along the Canada–United States border. It includes a new six-lane bridge
across the Detroit River, associated border inspection plazas, and connections
to the freeway systems in Ontario and Michigan. In the summer of 2024, work to
connect the bridge deck between Windsor and Detroit, was completed, with the
bridge becoming an official border crossing. Completion of the project is planned
for September 2025, with the first vehicles expected to travel across the bridge.
13
2024 Rank: 12
Location: Windsor, Ont. to Detroit, Mich.
Owner: Windsor-Detroit Bridge Authority (WDBA)
Project/Construction Manager: Deloitte
DBFOM Team: Bridging North America—ACS Infrastructure Canada Inc.; Fluor
Canada Ltd.; Aecon Concessions; RBC Dominion Securities Inc.; AECOM; Carlos
Fernandez Casado S.L/FHECOR Ingenieros Consultores, S.A.; Moriyama & Teshima
Architects; Smith-Miller + Hawkinson Architects LLP; Dragados Canada Inc.; Aecon
Infrastructure Management Inc.; Turner Construction Company; Aecon O&M, a
division of Aecon Construction Group Inc.; DBI Services, LLC; URS Federal Services,
Inc. (AECOM)
Engineer: Parsons (owner’s engineer); Arcadis-IBI Group (design); Stantec; COWI
(design)
Other Key Players: EY (advising team); Golder (WSP) (geotechnical and
foundation engineering); Hanscomb (owner’s cost consultant and special advisor);
Kasian (PDC team); LeighFisher (lender’s technical advisor INTECH (risk advisor);
CIMA+ (transmission relocation design); WSP (Environmental Services); Aon (risk
advisor); Parsons (bridge technical advisor); Tetra Tech; Rider Levett Bucknall; A.W.
Hooker Associates Ltd. (cost consultant); Canam Group; Englobe; EXP (engineering
and testing services); Wood (WSP) (materials tester); Mulvey & Banani; HKA,
Accuracy (management consultant); Egis
Suppliers: Entro (signage and wayfinding); Victaulic
Legal: Fasken Martineau DuMoulin (transaction advisor); Blake, Cassels & Graydon
(legal advisor to the proponent); Dentons; Borden Ladner Gervais; Singleton
Urquhart Reynolds Vogel LLP
Funding: P3
Substantial Completion: 2025
LRT
Surrey Langley
SkyTrain
$6 BILLION
The Surrey Langley SkyTrain Project is a 16-kilometre extension of the Expo Line. Major construction began
in 2024, with guideway, stations, and systems and trackwork contractors now in place. Once complete, people
in the region will be able to travel between Langley City and Surrey Centre in approximately 22 minutes and
between Langley and downtown Vancouver in just more than an hour.
32
WDBA
Gordie Howe
International Bridge
$6.4 BILLION
RENEW CANADA – TOP100 2025
2024 Rank: 20
Location: Surrey/Langley, B.C.
Owner: Province of British Columbia (The
Transportation Investment Corporation is leading
the delivery of the project on behalf of the Ministry
of Transportation and Infrastructure)
SkyLink Guideway Partners (DBF for the elevated
guideway and associated roadworks, utilities and
active transportation elements): Dragados Canada
Inc.; Ledcor Investments Inc.; Ledcor Mining Ltd.
South Fraser Station Partners (build 8 new
stations): Aecon Constructors; Acciona Infrastructure
Canada Inc.; Pomerleau BC Inc.
Transit Integrators BC (design and build the
systems and trackwork): AtkinsRéalis Major Projects
Inc.; AtkinsRéalis Canada Inc.; Western Pacific
Enterprises Ltd.
Engineer: Hatch (lead engineer); Westco, DIALOG;
AECOM (design); COWI (owner’s); McElhanney
(design); EXP (engineering design)
Other Key Players: Deloitte; Golder (WSP)
(geotechnical studies); Ausenco; Charter PDI;
Hanscomb (cost consultant); Stantec (early works);
Parsons; Colliers Project Leaders; EY (advisory
services); GeoVerra (early works); Egis; INTECH (risk
advisor); Turner & Townsend (cost consultant)
Legal: Norton Rose Fulbright; Borden Ladner
Gervais
Funding: Public
Substantial Completion: 2029