Roberts Bank Terminal 2
$3 BILLION
Roberts Bank Terminal 2 involves the construction
of a trade-enabling three-berth marine container
terminal on new federally-owned land, built in subtidal
waters to minimize environmental effects. The terminal
will increase container terminal capacity by more
than 30% on Canada’s west coast, strengthening
reliable access to goods Canadians use every day, and
playing a key role in supporting Canadian exporters to
increase trade with economies around the world.
The project includes: construction of new land
and a wharf that will accommodate a new marine
container terminal with a throughput capacity of up
to 2.4 million twenty-foot equivalent (TEU) containers
annually; a widened causeway to accommodate ad-
28
ditional road and rail infrastructure and link existing
networks to the marine terminal; an expanded tug
basin for additional tugs; and environmental projects,
such as habitat offsetting, construction mitigation
programs, and a monitoring follow-up program.
The Government of Canada and Government of B.C.
approved the project in 2023, after a rigorous federal
and provincial environmental assessment process. Before construction can begin, more steps are required,
including obtaining a Fisheries Act Authorization,
ongoing consultation and collaboration with First
Nations, engagement with local communities, continued market condition assessment, procurement, and
preparation for a final investment decision.
HEALTHCARE
Surrey Hospital and
B.C. Cancer Centre
$2.88 BILLION
The first of its kind in British Columbia, the new Surrey hospital and B.C. Cancer Centre
will be a fully digitally equipped, fully electric facility that will be at the forefront of health
care innovation, technology and sustainability. The new state-of-the-art hospital will provide increased capacity in areas such as emergency, surgical, inpatient, ambulatory care,
medical imaging, laboratory, pharmacy, and cancer care services, to support thousands
of additional patients every year. The new hospital and cancer centre will feature 168
acuity-adaptable inpatient beds, a surgical/perioperative suite with five operating rooms,
four procedure rooms, and an emergency department with 55 treatment spaces.
29
2024 Rank: 28
Location: Surrey, B.C.
Owner: Fraser Health Authority
DB Team: EllisDon Design Build Inc.
Architects: Parkin Architects Ltd.; ZGF Architects Inc.
Other Key Players: Arcadis IBI Group (owner’s technical advisor); WSP
(preliminary design); Stantec (consulting engineer); Hatch (environmental
engineer); Victaulic (supplier); Cartel Communications, Inc.; McElhanney
(site surveyor); EXP (owner’s geotechnical engineer); EY (management
consultant); H.H. Angus & Associates Limited Consulting Engineers
(engineer-design); INTECH (risk advisor)
Legal: Bennett Jones SLP
Funding: Public
Substantial Completion: 2029
SUBWAY
Broadway
Subway Extension
$2.8 BILLION
The Broadway Subway Project will see the addition of six underground stations and 5.7 kilometres of track to the Millennium
Line. The extension will run from VCC-Clark Station to Arbutus
Street; 700 metres will be elevated guideway and the remainder
will be tunneled. The commute from VCC-Clark to Arbutus Station
will take 11 minutes, saving the average transit commuter almost
30 minutes a day and will relieve congestion along Broadway. In
2024, tunnel boring operations finished, marking the completion
of the most technically complex and challenging part of the new
subway construction.
48
2024 Rank: 27
Location: Delta, B.C.
Owner: Vancouver Fraser Port Authority
Engineer: Moffatt & Nichol (owner’s
engineer); Stantec (engineering and design);
AECOM (engineer-environmental); Parsons
(engineer-planning); WSP (marine/highway/
bridges/buildings, geotechnical, construction
management, quality assurance—reporting
to PM, construction contract administration,
geomatic scanning
Environmental Services: Ecofish; Ecowest; Ausenco;
Golder (WSP) (environmental & geotechnical
services); Ventus, BlueDot
Other Key Players: KPMG (procurement advisory);
Hamburg Port Consultants (terminal operations);
McElhanney (site surveyor)
Legal: Blake, Cassels & Graydon LLP; Fasken
Martineau DuMoulin LLP (legal advisor)
Substantial Completion: 2030+
RENEW CANADA – TOP100 2025
2024 Rank: 29
Location: Vancouver, B.C.
Owner: Province of British Columbia
(The Transportation Investment Corporation
is leading the delivery of the project on
behalf of the Ministry of Transportation and
Infrastructure)
DBF Team: The Broadway Subway Project
Corporation – A joint venture of Acciona
Infrastructure Canada Inc. and Ghella
Canada Ltd.
Other Key Players: Arcadis-IBI Group /
DIALOG BC Architecture Engineering Interior
Design Planning Inc. / Mott MacDonald
Canada Ltd. / Parsons Inc / Norland / BD
Hall, Golder (WSP) (geotechnical services);
McElhanney (site surveyor); HKA (management
consultant); Associated Engineering (quality
control); Aon, INTECH (risk advisor); Hanscomb
(cost consultant); Stantec (early works); Wood
(WSP) (consulting engineer/geotechnical
studies); EXP; Hatch; Colliers Project Leaders;
GeoVerra (site surveyor); Kontur (geotechnical
services); Cartel Communications, Inc.; KPMG;
Turner & Townsend (cost consultant)
Legal: Norton Rose Fulbright (owner’s advisor)
Funding: Public
• Federal: $896.9 million
• Provincial: $1.82 billion
• Municipal: City of Vancouver: $99.8 million
(in-kind land contribution)
Substantial Completion: 2027