TOP100 2025 Report - Report - Page 60
47
METRO VANCOUVER
There are over 20 projects
planned as part of the onsite
improvements of the Annacis Island
Wastewater Treatment Plant. Key
improvement projects include new
trickling filters, secondary clarifiers,
and a co-generation facility to make
better use of green energy captured
on site. Detailed design of the
remaining Phase 2 Final Works is underway with construction anticipated
to commence in 2026. A new digester
and biosolids dryer have been added
to the expansion program.
2024 Rank: 45
Location: Delta, B.C.
Owner: Metro Vancouver
Construction Manager: Hatch (outfall project); CDM Smith (Overall Construction
Coordination)
Contractors: Phase 1 Substantially Complete; Maple Reinders Inc. (Phase 2
Gravity Thickeners and Aeration Tanks Retrofit); Bennett Mechanical Installations
(Phase 2 Digester Heat Exchangers Upgrade); Pomerleau-Bessac General
Partnership (outfall pipeline); Graham
Engineers: Brown and Caldwell, Klohn Crippen Berger, CDM Smith, WSP (Stage 5 expansion); CDM Smith, WSP (materials engineering and testing); Golder (WSP) (outfall);
Wood (WSP) (consulting engineer/geotechnical studies & materials tester); McMillen
Jacobs, Arup (design architect); EXP (geotechnical); Hatch (tunnel design review and
outfall construction management); Colliers Project Leaders; Jacobs; CDM Smith; Associated Engineering (project and construction management/staff augmentation); Envirowest (environmental); McElhanney (consulting); Victaulic (supplier); E.S. Fox
Legal: Norton Rose Fulbright (for Metro Vancouver)
Funding: Public
Substantial Completion: (Phase 2 Early Works) 2025; (Outfall) 2025;
(Phase 2 Final Works) 2032
HEALTHCARE
Richmond Hospital
Redevelopment
$1.96 BILLION
The Richmond Hospital Redevelopment Project will be conducted
over four phases between 2022 and 2031. It is currently in Phase one:
Park Centre and Rotunda decant and demolition. This project includes
a new nine-floor acute care tower—the Yurkovich Family Pavilion—that
will add 113 new beds to the hospital bringing the total to 353 beds.
This project will feature a state-of-the art emergency department and
intensive care unit, a fully equipped medical imaging department, a
pharmacy and short-stay pediatrics unit to bring more services and
better care for people in the growing Richmond community. The South
Tower and the Milan Ilich Pavilon will also be renovated.
2024 Rank: 72
Location: Richmond, B.C.
Owner: Vancouver Coastal Health
Other Key Players: Turner & Townsend (cost
consultant)
Funding: Public
· Provincial: $1.89 billion
· Vancouver Coastal Health: $30 million
· Richmond Hospital Foundation: $40 million
Substantial Completion: 2031
VANCOUVER COASTAL HEALTH
46
WATER/WASTEWATER
Annacis Island Wastewater
Treatment Plant Expansion
$2 BILLION
NEW
Red Deer Regional Hospital
Centre Redevelopment
$1.8 BILLION
There are two major components of this redevelopment:
· Project 1: construction of a new patient tower and expansion and
renovation of the existing hospital’s main building
· Project 2: construction of an ambulatory building
The project will upgrade several services throughout the hospital
site including: an additional patient tower; six new operating rooms;
new Medical Device Reprocessing department; new cardiac catheterization labs; renovations to various areas within the main building;
newly renovated and expanded emergency department, and; and a
new ambulatory clinic building to be located adjacent to the surface
parkade.
60
RENEW CANADA – TOP100 2025
Location: Red Deer, Alta.
Owner: Alberta Health Services
Developer: Alberta Infrastructure
Construction Manager: Clark Builders
Architect: DIALOG
Other Key Players: EY (management consultant);
INTECH (risk advisor); KPMG
Legal: Bennett Jones SLP
Funding: Public
Substantial Completion: 2031
ALBERTA HEALTH SERVICES
48
HEALTHCARE