TOP100 2025 Report - Report - Page 67
64
REMEDIATION
Port Hope Area Initiative
$1.3 BILLION
The Port Hope Area Initiative (PHAI) is a federal environmental clean-up program. Its
mandate is the remediation and local, long-term, safe management of approximately
$1.7 million cubic metres of historic low-level radioactive waste in the municipalities of
Port Hope and Clarington in southern Ontario. The historic waste resulted from the radium and uranium refining operations of the former Crown corporation, Eldorado Nuclear
Limited, and its private sector predecessors, which operated until 1988.
The PHAI has two projects: the Port Hope Project and the Port Granby Project.
The Port Hope Project involves the construction of an engineered above ground
mound and supporting infrastructure for the safe, long-term management of approximately $1.2 million cubic metres of historic low-level radioactive waste, cleanup of
the waste from various major sites and small-scale sites in Port Hope and transportation of the waste to a new long-term waste management facility (LTWMF) currently
under construction. After the facility is capped and closed, anticipated to be in 2025,
ongoing maintenance and monitoring will continue for many years.
65
2024 Rank: 58
Location: Port Hope and Clarington, Ont.
Owner: Atomic Energy Canada Ltd., Natural Resources Canada
Project/Construction Manager: Canadian Nuclear Laboratories
Contractor: Wood (WSP)-CB&I Joint Venture; ECC/Quantum Murray Limited
Partnership; Maple Reinders; Kenaidan Contracting Ltd.; Northwind Portage;
Milestone Environmental; WSP (engineer); Graham
Engineer: GHD/MMM Joint Venture; AECOM (consulting); Wood (WSP)
(consulting/design/environmental)
Environmental Services: Golder (WSP) (contamination investigation/
remediation; Phase I ESA; geotechnical services); Arcadis-IBI Group; Dillon
Consulting; EXP (environmental consulting)
Other Key Players: Hanscomb (owner’s preliminary design stage
cost consultant and special advisor); Tetra Tech; E.S. Fox; Colliers
Project Leaders; CIMA+; Aon (risk advisor); Bird Construction; Turner &
Townsend (cost consultant)
Financiers/Banks: Natural Resources Canada
Legal: Osler; Torys (acted for the lender)
Funding: Public
• Federal: Atomic Energy of Canada Ltd.: $1.28 billion
Substantial Completion: Port Hope Project—2025
HEALTHCARE
Trillium Health Partners—The Gilgan
Family Queensway Health Centre
$1.3 BILLION
The 600,000-square-feet Gilgan Family Queensway Health Centre will include a
new patient tower, including a modern nine-story facility with over 350 beds and fully private patient rooms to ensure privacy and enhance infection prevention control.
The expanded space will also allow TPH to connect more people to specialized care,
including complex continuing care and rehabilitation services. Site preparation work
began in February 2024 with a ground-breaking held in April. Patient tower occupancy and final completion is planned for 2029.
2024 Rank: 64
Location: Etobicoke, Ont.
Owner: Trillium Health Partners
Procurement Manager: Infrastructure Ontario
Design-Build Contract: EllisDon Corporation
Consultants: Stantec Architecture Limited (Prime Consulting Services);
Colliers Project Leaders (Procurement Services); H.H. Angus & Associates Limited
Consulting Engineers (ICAT Systems Consultant)
Other Key Players: Accenture (project manager); Hanscomb (cost consultant);
Aon (risk advisor)
Legal: Gowlings: Borden Ladner Gervais (for the owner)
Funding: P3
Substantial Completion: 2029
NEW
66
PUBLIC SPACES
Calgary Rivers District
and Event Centre
$1.22 BILLION
Location: Calgary, Alta.
Owner: City of Calgary/Calgary Stampede/Calgary Sports and Entertainment
Corporation
Development Manager: CAA Icon
Construction Managers: Cana Construction, Mortenson
Prime Design Consultants: DIALOG, HOK
Other Key Players: Aon, INTECH (risk advisor)
Legal: Bennett Jones SLP
Funding:
· City of Calgary: $537.3 million
· Calgary Sports and Entertainment Corp.: $356 million
· Province of Alberta: $330 million
Substantial Completion: 2027
CITY OF CALGARY
This project is more than just a new Event Centre (Scotia Place). It
includes a number of improvements to the area including: a new 4-lane
underpass under the CP train tracks with wide sidewalks at 6th Street
S.E.; a community rink, outdoor and indoor gathering spaces; Scotia
Place and additional hosting space on a 10-acre parcel of land; and
improvements to 5 Street S.E and 15, 17 and 25 Avenues S.E.